E-Rate Organizer Utilization Summary Chart

Applicant:CLYDE-SAVANNAH CTRL SCH DIST
Billed Entity:124889
  FY Req.
FRNs
Funded
FRNs
486
on File
Requested
Amount
Committed
Category 1
Committed
Category 2
Total
Committed
Total
Disbursed
Remaining
Balance
Util.
%
  2018 0 0 0 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 0%
  2017 2 2 2 $637.78 $637.78 $0.00 $637.78 $393.41 $244.37 62%
  2016 2 2 2 $1,550.54 $1,550.54 $0.00 $1,550.54 $844.22 $706.32 54%
  2015 2 2 2 $1,846.59 $1,846.59 $0.00 $1,846.59 $1,652.86 $193.73 90%
  2014 2 2 2 $3,329.00 $3,329.00 $0.00 $3,329.00 $2,742.54 $586.46 82%
  2013 2 2 2 $3,055.15 $3,055.15 $0.00 $3,055.15 $2,342.16 $712.99 77%
  2012 2 2 2 $2,131.29 $2,131.29 $0.00 $2,131.29 $2,131.29 $0.00 100%
  2011 5 5 5 $7,072.88 $7,072.88 $0.00 $7,072.88 $2,049.40 $5,023.48 29%
  2010 7 7 7 $17,137.53 $17,137.53 $0.00 $17,137.53 $4,928.23 $12,209.30 29%
  2009 6 6 6 $16,511.60 $15,133.18 $0.00 $15,133.18 $15,133.18 $0.00 100%
  2008 7 7 7 $14,262.78 $12,466.58 $0.00 $12,466.58 $12,466.58 $0.00 100%
  2007 7 7 7 $16,667.78 $14,353.77 $0.00 $14,353.77 $14,353.77 $0.00 100%
  2006 7 7 7 $14,445.95 $14,692.20 $0.00 $14,692.20 $12,510.02 $2,182.18 85%
  2005 6 6 6 $13,867.06 $13,867.06 $0.00 $13,867.06 $13,322.41 $544.65 96%
  2004 9 9 9 $9,500.56 $9,500.56 $0.00 $9,500.56 $6,619.81 $2,880.75 70%
  2003 9 9 9 $9,735.36 $9,735.36 $0.00 $9,735.36 $5,432.93 $4,302.43 56%
  2002 37 14 9 $824,068.16 $16,209.82 $0.00 $16,209.82 $6,618.72 $9,591.10 41%
  2001 9 9 9 $8,300.76 $8,300.76 $0.00 $8,300.76 $6,517.35 $1,783.41 79%
  2000 6 4 4 $31,105.97 $5,593.60 $0.00 $5,593.60 $5,254.28 $339.32 94%
  1999 7 7 7 $30,353.81 $9,714.43 $17,604.00 $27,318.43 $3,839.01 $23,479.42 14%
  1998* 4 4 4 $15,939.00 $15,939.00 $0.00 $15,939.00 $4,304.62 $11,634.38 27%

 

Service Legend: Category 1 includes Telecomm, Voice, Data Transmission and/or Internet Access; Category 2 includes Internal Connections, Internal Connections Maintenance and Managed Internal Broadband Services

*Recurring service funding for FY 1998 was expanded from twelve to eighteen months to align original requests with the new fiscal funding year ending June 30, 1999.
[Last update: 04/29/2024]